Project Woodlands Week 6
Sep 27
Week 6 27/09/15
Overnight Monday and Tuesday this week brought torrential rain and we woke to find water dripping into the wall where our consumer unit and electric meter are housed and also dripping down one of the old chimneys onto our central heating boiler. This was however promptly dealt with and thankfully the rest of the week was dry.
The carpenters started on site on Thursday setting up the wood for the new gable end and on Friday the brick layer built up a large amount of the gable block work.
This weekend we have done some work in the front bedroom, removing the remainder of the coving and stripping the top layer of plaster from the internal wall.
Tomorrow the carpenters will be back to push on with the roof work and we are relieved to see the weather forecast for this week is good.
- gable end roof in progress
- gable end roof in progress
- block work on gable end
- block work on gable end
- block work on gable end
- block work on gable end
- gable end detail
- steel and block work detail
- joists detail
- joists over steel detail
- front bedroom
- front bedroom ceiling
- front bedroom ceiling
- front bedroom